Live Data Tracker

New York data center & large-load pipeline

Every data center, chip fab, and large industrial load asking to connect to New York's grid — straight from the NYISO interconnection queue, the earliest public signal a major facility is coming. These projects will need structured cabling, fiber trunks, DAS, security and access control years before a shovel hits dirt.

Source data as of 15 Jul 2026 · checked 2026-07-20 · refreshed automatically

69NY projects in queue
16.1 GWrequested peak load
4under construction / in test
Northbusiest zone (3,390 MW)

Where the load is landing

The pipeline concentrates upstate — cheap hydro around Massena and the North Country, the STAMP mega-site in Genesee County, and the Micron fab cluster outside Syracuse — with a second wave in the Hudson Valley. For context, 16.1 GW of requested load is roughly a third of New York's record summer peak demand.

Zone D North — 7 projects, 3,390 MWZone E Mohawk Valley — 12 projects, 3,167 MWZone A West — 12 projects, 2,715 MWZone C Central — 11 projects, 2,336 MWZone F Capital — 12 projects, 1,579 MWZone H Millwood — 2 projects, 1,200 MWZone B Genesee — 3 projects, 625 MWZone K Long Island — 3 projects, 597 MWZone G Hudson Valley — 7 projects, 519 MW

The full queue

All active New York large-load interconnection requests, largest first:

MWProjectDeveloperCountyZoneStatusFiled
1,935 St. Lawrence Infrastructure 2 St. Lawrence Infrastructure, LLC St. Lawrence D — North System Impact Study Pending 2025-09
1,000 1 Gig Data Center East Fishkill, NY Donovan Drive Holdings LLC Dutchess H — Millwood System Impact Study in Progress 2025-07
860 St. Lawrence Infrastructure 1 St. Lawrence Infrastructure, LLC St. Lawrence E — Mohawk Valley System Impact Study Pending 2025-09
576 Micron Fab 2 Micron New York Semiconductor Manufacturing LLC Onondaga C — Central Facilities Study in Progress 2023-10
500 North East Data LLC Data Center North East Data LLC Niagara A — West System Impact Study Pending 2025-08
480 White Pine Phase 1 Micron New York Semiconductor Manufacturing LLC Onondaga C — Central Under Construction 2023-03
467 Arsenal Data Site 1000 Arconic Corporation St. Lawrence E — Mohawk Valley System Impact Study in Progress 2025-03
435 North Country Data Center North Country Data Center St. Lawrence D — North Under Construction 2020-01
400 Incremental Load Request for Remington Factory Redevelopment Turin Management LLC Herkimer E — Mohawk Valley System Impact Study in Progress 2025-08
300 WNY STAMP Genesee County Economic Devel. Genesee B — Genesee Under Construction 2016-09
300 580 STAMP load increase GCEDC Genesee B — Genesee Under Construction 2022-12
300 Data & Technology Campus Riverview Innovation & Technology Campus, Inc. Erie A — West System Impact Study in Progress 2025-01
300 New York State Artificial Intelligence Data Center ZeroC Data Centers, LLC St. Lawrence E — Mohawk Valley System Impact Study in Progress 2025-03
270 Ranalli SuperDC Ranalli SuperDC LLC Onondaga C — Central System Impact Study in Progress 2025-05
250 Somerset Load Somerset Operating Company, LLC Niagara A — West In Service (Commercial) 2019-05
250 Lake Mariner Data II Lake Mariner Data LLC Niagara A — West System Impact Study Approved 2024-01
250 Wulf Compute Data Center II TeraWulf Brookings LLC Niagara A — West System Impact Study in Progress 2025-03
250 Pontoon Bridge Road Data Center American Data Center Partners LLC St. Lawrence E — Mohawk Valley System Impact Study Pending 2025-10
250 Broome County Tech Park The Agency Broome C — Central System Impact Study Pending 2025-10
233 Arsenal Data Site 250 Arconic Corporation St. Lawrence E — Mohawk Valley System Impact Study in Progress 2025-03
233 Arsenal Data Site 500 Arconic Corporation St. Lawrence E — Mohawk Valley System Impact Study in Progress 2025-03
200 St Lawrence Data and Agricultural Center ZeroC Data Centers, LLC St. Lawrence D — North Cost Allocation Accepted / IA in Progress 2021-06
200 Proposed Datacenters at 450 Broadway, Buchanan, NY, 10511 Holtec Decommissioning International (HDI) Westchester H — Millwood System Impact Study in Progress 2024-08
200 Greenidge 200 MW Data Center Project Greenidge Generation, LLC Yates C — Central System Impact Study in Progress 2024-12
200 Globe Digital Holdings - 1 GLOBE DH LLC Niagara A — West System Impact Study Pending 2025-10
200 GLOBE DH 2 GLOBE DH LLC Niagara Falls A — West System Impact Study Pending 2025-10
200 Globe DH 3 GLOBE DH LLC Niagara Falls A — West System Impact Study Pending 2025-10
200 Massena Development LLC Power Allocation North Country Data Center LLC St. Lawrence D — North System Impact Study Pending 2025-10
180 Kenwood Tech Center EKG Group LLC Albany F — Capital System Impact Study Pending 2025-11
176.6 Brookhaven Logistics Center WF Industrial XII LLC Suffolk K — Long Island Facilities Study Pending 2024-10
162 Cayuga Data Cayuga Operating Company, LLC Tompkins C — Central System Impact Study in Progress 2025-03
150 iPark 84 Data Center Interconnection iPark East Fishkill LLC Dutchess G — Hudson Valley System Impact Study in Progress 2026-03
150 NYISO Load Interconnection Process - Data Center Inquiry URI TALY Horseheads C — Central Scoping Meeting Pending 2026-04
140 Niagara Digital Campus Niagara Falls Redevelopment LLC Niagara A — West Facilities Study in Progress 2024-04
120 SDC St. Lawrence Sabey Data Center Properties, LLC St. Lawrence D — North System Impact Study Approved 2021-12
100 Remington Factory Redevelopment Turin Management LLC Herkimer E — Mohawk Valley System Impact Study in Progress 2025-05
88 Cayuga Compute Cayuga Operating Company, LLC Tompkins C — Central System Impact Study Approved 2024-04
66 Griffiss Park Triangle Development Griffiss Utility Services Corporation Oneida E — Mohawk Valley System Impact Study in Progress 2025-06
60 Greenidge Load Greenidge Generation LLC Yates C — Central Facilities Study Pending 2018-10
60 Al Tech Steel Site Advance Albany County Alliance Albany F — Capital System Impact Study Pending 2025-10
50.2 Digihost load Digihost Technologies, Inc. Niagara A — West In Service (Commercial) 2022-11
50 Cayuga Load Cayuga Operating Company, LLC Cayuga C — Central Facilities Study Pending 2019-05
50 POWI Project P&M Brick LLC Albany F — Capital System Impact Study Approved 2023-11
50 Hudson Valley Data Center Robert Delcalzo Rockland G — Hudson Valley Cost Allocation Accepted / IA in Progress 2024-07
50 OOWWTP Expansion Program Onondaga County Department of Water Environment Protection Onondaga C — Central System Impact Study Pending 2025-10
45 Site Master Plan Expansion Phase I Research Foundation of SUNY Albany F — Capital System Impact Study Pending 2025-12
40 Luther Forest National Grid Saratoga F — Capital In Service (Commercial) 2005-11
40 Saratoga Expansion Robert Grant Saratoga F — Capital System Impact Study Pending 2026-03
22.3 Project Sycamore Orangeburg Project Sycamore - Orangeburg Rockland G — Hudson Valley Cost Allocation Accepted / IA in Progress 2024-06
20 Green Island Power Green Island Power Authority Albany F — Capital In Service (Commercial) 2008-04
20 New York State Dept. of Health Lab (Harriman Campus, Albany NY) New York State Office of General Services Albany F — Capital System Impact Study Pending 2025-11
20 GE Vernova 2690 Balltown Road High Yard Upgrade GE Vernova Schenectady F — Capital System Impact Study Pending 2026-01

Reading the pipeline: what's actually happening

The Massena / North Country cluster

St. Lawrence County alone accounts for several gigawatts of requests — including the two largest in the state — drawn by low-cost St. Lawrence River hydro and former aluminum-plant sites with existing heavy interconnection. Land clearing has begun on some sites while others face vocal local opposition.

Micron's Clay megafab

The anchor tenant of upstate load growth: a chip-fab campus north of Syracuse with over 1 GW requested across two phases, first concrete poured in July 2026. Fabs are among the most low-voltage-intensive buildings ever constructed.

Albany is deciding the rules

A statewide bill imposing a one-year permitting moratorium on data centers over 20 MW passed both houses in June 2026 and awaits the Governor's signature, while the Public Service Commission (Case 26-E-0045) is rewriting how large loads pay for grid upgrades. Position in this queue is about to matter even more.

The grid is the constraint

NYISO's Power Trends 2026 puts the statewide summer capacity margin at roughly 417 MW — against 16.1 GW of requested new load. Projects with accepted cost allocations and executed interconnection agreements are the ones to watch; the rest are competing for headroom that doesn't exist yet.

Why a low-voltage network publishes this

A data center or fab appears in this queue one to four years before general contractors bid the work — which is exactly when Division 27/28 scope gets budgeted: data hall cabling and fiber trunking, perimeter and interior security, access control, and DAS/ERRCS coverage. If you're a developer, owner's rep, or GC on any project above, our network scopes that work statewide — including prevailing-wage compliance where public money is involved.

Methodology & attribution

Data: NYISO Interconnection Queue, Load Projects (official workbook at nyiso.com/interconnections), retrieved 2026-07-20. This page is an independent, derived presentation of public regulatory data; Low Voltage New York is not affiliated with NYISO. Non-NY rows (projects interconnecting to NYISO from neighboring states) are excluded. Status labels follow NYISO's published legend. We re-check the source weekly and republish when it changes; NYISO typically refreshes the queue monthly. Context items are sourced from NYISO Power Trends 2026, PSC Case 26-E-0045, and public reporting.